Risk Management Practices and Military Construction Projects in Nigeria
HAMMED, Olawale Gazal1 (PhD), DOSUNMU-ADEBOLA Rasaq Oluwashikemi, OLADELE, Waheed Olatunji, AZEEZ Taofeekat Oyindamola
Abstract
The construction industry has inadequate approach for managing risk
and is highly risk-inclined. Several construction projects in Nigeria and
throughout the world are prone to risk, despite the best efforts of all
parties involved, they still have a high probability of performing poorly
due to huge overbudgets and delivery delays. Therefore, this study
intends to evaluate the risk management practices applied to
construction project in military system in Nigeria. For the study, a
survey research design approach was used. Data were gathered
through the use of a standardized questionnaire. The sample size of the
project's stakeholder includes 87 end users as well as 75 military
engineers was chosen using convenient, random and purposive
sampling techniques.70 usable questionnaire were return. The
construct and content of the questionnaire were both used to validate it.
The reliability was measured using Cronbach's Alpha, with ? = 0.86.
The data analysis employed was multiple regression analysis. The
findings of the study show that risk identification, monitoring and
response have significant relationship with the timely delivery of
military construction projects (R = 0.705; p<0.05; R2 = 0.645). From
the results of the findings, it can be explained that managing the risk
does not primarily mean avoiding risk but identifying it correctly and
determining all associated opportunities and hazards, which will
promote adequate response and mitigate the effects of the risk. The
study recommended among others that risk management should be
included in the curriculum as an examinable subject for all military
cadets undertaking construction-related studies.
Keywords
Risk Identification, Risk Management, Risk Monitoring, Risk Response, and Timely Delivery
Full Text
Download
References
Agerberg, J. (2012). Risk management in tendering process (Master’s thesis). Chalmers University of
Technology.
Aleshin, A. (2017). Risk management of international projects in Russia. International Journal of Project
Management, 35(1), 207–222.
Baloi, D., & Price, A. (2003). Modelling global risk factors affecting construction cost performance.
International Journal of Project Management, 21(4), 261–269.
Banaitien?, N., & Banaitis, A. (2012). Risk management in construction projects. Procedia Engineering,
57, 312–318.
Belel, Z., & Mahmood, H. (2012). Risk management practices in the Nigerian construction industry.
Journal of Engineering Sciences, 7(3), 1–6.
Bing, L., & Tiong, R. (2016). Risk management of international construction joint ventures. Journal of
Engineering and Management, 10(2), 277–288.
Cooper, D. F., Grey, S., Raymond, G., & Walker, P. (2005). Project risk management guidelines. John
Wiley & Sons.
Dosunmu, O. (2018). Assessment of the likelihood of risk occurrence on tendering and procurement of
construction projects. Journal of Construction Business and Management, 2(1), 20–32.
https://doi.org/10.15641/jcbm.2.1.95
Fadun, O. S., & Saka, S. T. (2018). Risk management in the construction industry: Analysis of critical
success factors. International Journal of Development and Management Review, 13(1), 1–12.
Flanagan, R., Norman, G., & Chapman, R. (2016). Risk management and construction (2nd ed.).
Blackwell Publishing.
Hillson, D. (2000). Effective opportunity management for projects. Marcel Dekker.
Hwang, B., Zhao, X., & Chin, E. (2017). International construction joint ventures. Journal of
Engineering, Construction and Architectural Management, 24(2), 209–228.
Iqbal, A. (2015). Risk management framework for construction projects. International Journal of Project
Management, 23(1), 25–35.
Kartam, A. K., & Kartam, N. A. (2018). Risk and its management in the Kuwaiti construction industry.
International Journal of Project Management, 9(1), 325–335.
Lawrence, M. (2015). Effect of risk management at project planning phase on construction performance
in Rwanda (Master’s thesis). Jomo Kenyatta University of Agriculture and Technology.
Lee, J. H., Jin, B. S., & Ji, Y. (2009). Development of a structural equation model. International Journal
of Industrial Ergonomics, 39(3), 7–14.
Mhetre, K., Konnur, B., & Landage, A. (2016). Risk management in construction industry. International
Journal of Engineering Research, 5(1), 153–155.
Nnadi, E. O. E., Enebe, E. C., & Ugwu, O. O. (2018). Evaluating awareness of risk management.
International Journal of Construction Engineering and Management, 7(1), 47–52.
15
Olsson, R. (2007). In search of opportunity management. International Journal of Project Management,
25(8), 745–752.
Project Management Institute. (2004). A guide to the project management body of knowledge
(PMBOK® Guide). PMI.
Project Management Institute. (2016). A guide to the project management body of knowledge
(PMBOK® Guide) (6th ed.). PMI.
Shen, L. (2019). Project risk management in Hong Kong. International Journal of Project Management,
5(1), 101–105.
Tohidi, H. (2011). The role of risk management in IT systems. Procedia Computer Science, 3(1), 881
887.
Winch, G. (2010). Managing construction projects. Wiley-Blackwell.
Yu, M., & Nagurney, A. (2013). Competitive supply chain networks. European Journal of Operational
Research, 224(2), 273–282.